Difference between cost plan and budget
It is important not to confuse cost plans and budgets.
A budget is a statement of the amount of money available to spend over a period of time, or on a specific thing, such as a building. The budget is set by the client (although they make seek help to do this). It may include an outline plan for how that money will be spent, and a breakdown of the items it will be spent on. Budgets set a limit for expenditure and this can help determine what is affordable. They should be set as early as possible so that expectations can be managed. It is important that they are based on evidence and that they are realistic, rather than simply stating the amount of money available, or being a wild guess, because, once the budget is set in people's minds, it can be very difficult to change.
For more information see: Budget.
Cost plans are typically prepared by a cost consultant and provide an estimate of what the actual costs are likely to be. Cost plans evolve through the life of the project, developing in detail and accuracy as more information becomes available about the nature of the project. They can range from very early initial cost appraisals through to tender pricing documents and the final account. If the cost plan exceeds the budget, it may be necessary to reduce the cost or scope of the project.
For more information see: Cost plan.
[edit] Related articles on Designing Buildings
- Budget.
- Capital costs for construction projects.
- Construction costs.
- Cost control.
- Cost plans for construction projects.
- Cost management techniques used to monitor the cost of construction projects.
- Difference between collateral warranties and third party rights.
- Difference between preliminaries and preambles
- Elemental cost plan for design and construction.
- Final account.
- Outturn cost.
- Quantity surveyor.
- Tender pricing document.
Featured articles and news
International Electrician Day, 10 June 2025
Celebrating the role of electrical engineers from André-Marie Amperè, today and for the future.
New guide for clients launched at Houses of Parliament
'There has never been a more important time for clients to step up and ...ask the right questions'
The impact of recycled slate tiles
Innovation across the decades.
EPC changes for existing buildings
Changes and their context as the new RdSAP methodology comes into use from 15 June.
Skills England publishes Sector skills needs assessments
Priority areas relating to the built environment highlighted and described in brief.
BSRIA HVAC Market Watch - May 2025 Edition
Heat Pump Market Outlook: Policy, Performance & Refrigerant Trends for 2025–2028.
Committing to EDI in construction with CIOB
Built Environment professional bodies deepen commitment to EDI with two new signatories: CIAT and CICES.
Government Grenfell progress report at a glance
Line by line recomendation overview, with links to more details.
An engaging and lively review of his professional life.
Sustainable heating for listed buildings
A problem that needs to be approached intelligently.
50th Golden anniversary ECA Edmundson apprentice award
Deadline for entries has been extended to Friday 27 June, so don't miss out!
CIAT at the London Festival of Architecture
Designing for Everyone: Breaking Barriers in Inclusive Architecture.
Mixed reactions to apprenticeship and skills reform 2025
A 'welcome shift' for some and a 'backwards step' for others.
Licensing construction in the UK
As the latest report and proposal to licence builders reaches Parliament.
Building Safety Alliance golden thread guidance
Extensive excel checklist of information with guidance document freely accessible.
Fair Payment Code and other payment initiatives
For fair and late payments, need to work together to add value.
Pre-planning delivery programmes and delay penalties
Proposed for housebuilders in government reform: Speeding Up Build Out.
High street health: converting a building for healthcare uses
The benefits of health centres acting as new anchor sites in the high street.